Multi-Unit Development

Business Parks Contractor

Getting connected - new Multi-Unit Development

The information in this section describes the process for builders/developers who want to connect a new housing /apartment scheme or commercial/industrial development to the electricity network.

 

Important - Please contact us early when planning the project.

Connect a new Multi-Unit Development

Contact your local ESB Networks Area Office as early as possible when planning your project. We will arrange for you to have a preliminary discussion with our Design Team. Early contact means the electricity connection requirements can be incorporated into your project design from the beginning. This should prevent possible difficulties arising at a later stage.

Download the Application Form (PDF | 1MB) or call 1850 372 757 or +353 21 2386555 to request a copy.

Key items to include in your application

  • Correct format of CAD files and hard copies as specified in the application form

  • Exact details of the postal address of each unit as agreed with the Local Authority

  • The Maximum import Capacity (MIC) of each individual premise/commercial /unit.

  • You must also choose between 'Single Tariff 'or 'Time of Day Metering'

Apply for a connection