Before you proceed
Domestic New Connection
You have chosen to apply for a Domestic New Connection. This application process will take 10-15 minutes to complete. Please note this category applies to:
- Single homes on a new site
- Renovations to existing dwellings to accommodate a family apartment
- Farms requiring less than 29 kVA of electricity supply
- Out offices
Project Time Frame & Typical Pricing
We aim to provide a quote within 15 business days.
The typical charge for a single, standard connection is €3,486 and for a single enhanced connection (16 KVA) €4,721.
Once you have accepted the quote and made payment, we aim to complete your new connection within 60 business days.
While we will make every effort to meet these target timeframes, you may experience delays due to current high demand. We apologise for any inconvenience this may cause you.
Mandatory Information & Documentation
In order to provide you with a valid quote, accurate information must be provided in your application. The following are required to complete the application: