Skip to Content
For emergencies: Call 1800 372 999
Gaeilge

FOI Disclosure Logs

FOI10300

Status Refused
Date received 28 Jan 2021
Date of decision 24 Feb 2021
Category of requester Business / Interest Group
Details of request
  1. A copy of (i) the contract/agreement with Siro Limited in relation to the “capital contribution of network assets worth €0.9 million” which is referred to in page 25 and page 28 of the Siro accounts to year end 31 December 2019, (ii) the valuation/report on this transaction and (iii) a copy of the minutes of the meeting where this transaction was approved. 
  2. A copy of (i) the “network access agreement (IRU)” and (ii) the “business and asset transfer agreement” referred to in the Siro Limited annual accounts for year-end 31 December 2019. 
  3. A copy of (i) the valuations and/or reports carried out by or on behalf of ESB and/or ESB Networks DAC in relation to the “network asset agreement (IRU)” and/or “business and asset transfer agreement “ transaction of €100 million which is identified in page 25 the Siro Limited accounts and (ii) a copy of the minutes of the meetings where the €100 million deal/contract was approved (iii) and a copy of the decision to approve the transaction.
  4. Records showing the extent and nature of services provided to Siro Limited by ESB Networks DAC and/or ESB Networks relevant personnel in the past 12 months and the amounts paid by Siro Limited for those services.

FOI10295

Status Refused
Date received 18 Jan 2021
Date of decision 21 Jan 2021
Category of requester Client
Details of request

1. Number of engineering staff in your organisation who were paid or reimbursed either in part or full their annual membership fees for Engineers Ireland for the years 2018 and 2019.  

2. A list of all and any other professional subscriptions or membership fees (broken down by name of institution, and staff grade and number of each separately) either paid or reimbursed, party or fully, during 2018 and 2019.

FOI10294

Status Handled Outside FOI/Withdrawn
Date received 18 Jan 2021
Date of decision 26 Jan 2021
Category of requester Business / Interest Group
Details of request

ESB’s overhead line construction manual or a specification as we intend to build a new wind farm and need to assess the grid connection.

FOI10293

Status Withdrawn
Date received 15 Jan 2021
Date of decision 09 Feb 2021
Category of requester Client
Details of request

A copy of the report "DF08-03 AP01 Independent Expert Report on Long Term Investment Needs (Pictures of the Future)" that was sent to the CRU regarding PR5? 

Also can you send me the link for Poyry TNEI report that was used to inform the above document?

FOI10292

Status Granted
Date received 08 Jan 2021
Date of decision 01 Feb 2021
Category of requester Client
Details of request

a) Customer Minutes Lost on average per customer affected for storms during 2020. 

b) Longest period of outage (customer minutes lost) for more than 100 customers as a result of a storm in 2020.  

If the figures are not available for 2020, I will accept figures for 2019.

FOI10291

Status Withdrawn
Date received 17 Dec 2020
Date of decision 18 Dec 2020
Category of requester Business / Interest Group
Details of request

Can you please release the prioritisation list of projects to be processed under ECP2.1 

Can you please send on the list projects which qualified under the following categories; 

  • Battery Projects 

  • Top 25 Renewable Projects as set out under the ECP2 ruleset 

  • Projects by date order of planning 

  • NGPA

    Community projects

FOI10289

Status Refused
Date received 10 Dec 2020
Date of decision 06 Jan 2021
Category of requester Client
Details of request

All available details of the obligations of 

ESB Networks Ireland to US Department of Defense’s Defense Logistics Agency (DLA) and/or NATO wrt 

Commercial and Government Entity Code SYV18 

FOI10288

Status Part-Granted
Date received 21 Nov 2020
Date of decision 18 Dec 2020
Category of requester Business / Interest Group
Details of request
All data pertaining to the sale and subsequent development of the site at the ESB substation including legal agreement transferring ownership, conditions of sale, maps, any emails in relation to the sale of the site, advice or opinions sought by the developer in connection with the original and subsequent planning applications and also during the development at the site, documentation of any assessments made by ESB on the plans for the hobby workshop or any other changes made under the original planning granted, requests for meetings at the site by the developer, subsequent summary notes of any meetings which may have taken place following onsite meetings, correspondence, if any, with the developer in relation to the painting of the sub-station by the developer. I would like to receive this information in PDF format.

FOI10285

Status Part-Granted
Date received 09 Nov 2020
Date of decision 01 Dec 2020
Category of requester Journalist
Details of request

The details of all complaints made by residents of Longford, Leitrim and Roscommon, Cavan and Monaghan in tabular form, to ESB Networks between March 1st 2020 and November 9th 2020? Details of all actions taken by the ESB after complaints made by residents in Longford, Leitrim and Roscommon Cavan and Monaghan in tabular form, between March 1st 2020 and November 9th 2020?

FOI10284

Status Refused
Date received 09 Nov 2020
Date of decision 19 Nov 2020
Category of requester Client
Details of request
A copy of all email and other correspondence relating to planning, community consultation, commercial arrangements, contracts and planning permissions for the erection of masts for telephony and other purposes at the ESB Milltown station, Cowper Drive and Park Drive, Dublin 6.