Skip to Content
For emergencies: Call 1800 372 999
Gaeilge

Enduring Connection Policy (ECP)

What is the ECP?

The ECP process for grid connection applications is the current pathway for generators, storage, and other system services technology projects to connect to the electricity system. On 25th September 2024, the Commission of Regulation for Utilities (CRU) published its decision on Electricity Connection Policy – Generation and System Services (ECP-GSS) which sets policy for onshore renewable and conventional generators, storage, and other system services technology projects connecting to the electricity system. The System Operators are working with CRU on the actions outlined in this decision paper. For further information, please refer to the Electricity Connection Policy – Generation and System Services Decision Paper (CRU/2024101).

 

The ECP-2.5 application window for all Category A (batch) applicants closed on 30th November 2024. Successful applicants were prioritised by largest renewable energy generation (first 25), then by planning permission grant date with no more than 10 primarily storage and other system service technology projects. Please see the ECP-2.5 Category A initial Batch Results here and the initial ECP-2.5 Category B and C Batches here.

 

For further information, please refer to the ECP-2 Decision Paper (CRU/20/060), ECP-2 Ruleset and ECP-2.4 decision (CRU202326).

 

ECP-2.5 application categorisation

Under ECP-2.5, grid connection applications are categorised as follows:

 

CategoryDefinitionOffer TargetPrioritisation
AGeneration, storage, and other system services technology projects (MEC>0.5MW)70First 25 on largest renewable energy generators; remainder on earliest planning permission grant date; no more than 10 storage (where 100% of the MEC is storage) and other system service technology projects
BSmall projects (MEC>0.2MW and ≤0.5MW), DS3 system services trial projects (MEC≤0.5MW) and Autoproducers15Earliest application received complete date
C100% community-owned renewable energy projects (MEC≥0.5MW and ≤5MW)15Planning permission grant date and then by application form received complete date

 

Please refer to the Application Guide below when submitting your ECP-2.5 application. 

Application information and tools

Useful information and digital tools to guide you through the ECP-2 process.

Renewable hubs pilot

ESB Networks received CRU approval to begin a Renewable Hubs pilot at 5 locations as part of the ECP-2.4 application process, which includes per-MVA charging for shared assets, supporting the accelerating connection of renewables to the electricity system

Generator standard charges

The CRU published a decision paper (CRU/21/035) on ESB Networks 2020 proposals for changes to Generator Standard Charges (GSCs). The new 2025 ESB Networks "Standard Prices for Generator Connections 2025" document is published here.

Generation minimum cost calculator

Our interactive available capacity heatmap contains capacity information on our 3-phase LV, MV and HV DSO substations, to enable easy identification of potential transformer capacity in the vicinity of your site.

Generator availability capacity map

The generation minimum cost calculator provides an estimation of the minimum costs associated with generator connections to the Distribution System Operator (DSO) network >200kW.

Installed capacity cap review

On the 17th January 2024, the Commission for Regulation of Utilities (CRU) published a Decision Paper on the Installed Capacity Cap (ICC). Please see summary to the CRU decision.

Node assignment ruleset

The node assignment ruleset aims to establish an efficient screening process for allocating ECP-2 applications to the appropriate nodes at which the generation can connect to the Irish electricity grid.

Application guide

Application Fees

 

MIC and Installed AC Generation
Capacity Ranges

A
Demand Capacity (MIC)

B
Installed Generation Capacity (Including Non-Exporting Generation)

C
Shallow Works

Micro-generation*

€0

€0

€0

Mini-generation**

€0

€795

€0

Small-scale generation***

€0

€995

€0

Not covered above ≤ 500 KW€0€1, 888

€0

> 500kW ≤ 1 MW

€0

€10,722

€0

> 1 MW ≤ 2 MW

€7,560

€16,343

€0

> 2 MW ≤ 6MW

€15,121

€21,964

€0

> 6MW ≤ 10 MW

€26,145

€40,094
€41,837

> 10 MW ≤ 20MW

€42,978
€57,588
€47,938

> 100 MW

€58,852
€61,679
€54,539


Table 1 - Connection Offer Application Fees (excluding VAT) - 2025

Demand only: Fee = AMIC + CMIC - D
Generation Only: Fee = BIGC + CIGC - D
Demand and Generation: Fee = AMIC + BIGC + MAX [CIGC , CMIC] - D
Where D is the sum of the credits for the pre-feasibility and advanced works studies still relevant.     
Determination of D will be calculated by the relevant System Operator

 

*Micro-Generation is designed to operate in parallel with the electricity network and is a source of electrical energy rated up to and including 25 amperes (≈6kVA) at low voltage [230 volts], when the connection is single phase, or 16 amperes(≈11kVA) at low voltage [230/400 volt], when the connection is three-phase.

 

**Mini-Generation is designed to operate in parallel with the electricity network and is a source of inverter connected electrical energy, and all associated electrical equipment, where the Installed Generator Capacity is less than or equal to the MIC, and is in the range of 25 amperes (6kVA) to 72 amperes (17kVA), when the connection is single-phase or 16 amperes (11kVA) to 72 amperes (50kVA), when the connection is three-phase.

 

***Small Scale Generation is designed to operate in parallel with the electricity network and is defined as a source of connected electrical energy, and all associated electrical equipment, where the Installed Generator Capacity is less than or equal to the MIC, in is the following ranges: Inverter-connected Installed Capacity greater than 72amps (≈50kVA) at three phase and up to 200kVA, or, Synchronous Installed Capacity greater than 6kVA and up to 200kVA.

 

Modification Fees

Level

Initial non-refundable
deposit (excl. VAT)

Balance of fee
(excl. VAT)

Total Fee
(excl. VAT)

Level 1

€1,046

€0

€1,046

Level 1.5

€1,046

€5,260

€6,306

Level 2

€1,046

€10,521

€11,567

Level 2.5

€1,046

€15,964

€17,010

Level 3

€1,046

€21,407

€22,453

Level 3.5

€1,046

€25,830

€26,876

Level 4

€1,046

€30,252

€31,298


Table 2 - Modification Fees (ex-VAT @ 23%)

Useful documents

Can’t find what you’re looking for? We’re here to help.

Go to Customer support