Connecting a Non-Exporting Generator to the Electricity Network

Please note the process for applying for Non-Exporting (MEC=0) Generation will change from 1st January 2025. The new application process is outlined below and recognises that non-exporting connections are considered as normal generator connections but with an export level of zero (0).

Non-Exporting (MEC=0) Generators operate in parallel with the electricity distribution system. These generators cannot be used to export electricity onto the electricity network or to supply or sell electricity via the distribution network. 

Customers applying to install non-exporting generation must complete an application form for commercial and technical assessment. For further details on the relevant application forms please refer to the Step-by-Step guide at the bottom of this page.  

The details of this assessment, and any potential uprate works required, will be set out in the customer's connection offer. It is important that customers who are installing embedded generation, non-exporting capacity, read and understand the following documents:

For all non-exporting generators up to 200kVA, to standardize the method by which customers ensure they do not export onto the distribution network, an Export Limiting Scheme (ELS) must be installed. Where the ELS does not meet the given criteria a reverse power relay will also be required. For further detail please read Conditions Governing the Connection and Operation of Export Limiting Schemes at LV and MV (Download PDF | 1,435 KB)

For non-exporting generators above 200kVA, to standardize the method by which customers ensure that they do not export electricity onto the distribution system, a reverse power relay is required to trip either the embedded generation or the customer's facility, details of which will be set out in the connection offer. Please note that witness testing of the relay by ESB Networks will not normally require a ‘switch out’ to confirm relay operation. 

SCADA Equipment Requirement: 

A relatively recent modification [#36] to the Distribution Code, stipulates that customers installing non-synchronous, embedded generation with a total capacity of  >1MW, are required to be controllable by EirGrid. This necessitates the installation of Supervisory Control and Data Acquisition (SCADA) equipment, which includes Remote Terminal Unit (RTU), Distribution System Operator (DSO) SCADA, Polling  Radio and Batteries. Note that this applies even where there is no export of power from the site.

Standby Generators

A standby generator is used for emergency power generation in the event of the loss of mains electricity supply. It does not operate in parallel with mains supply. For more information on this, please see Standby Generators.

Step-by-Step Guide

Note

For Connections made after September 2018 some Distribution Code Conditions may change, arising from the need to be aligned with European Network Codes.

European Network Codes

If you wish to connect a generator that is intended to export energy onto the electricity network, please go to Generator Connections

Get in Touch
PHONE
1800 372 757